The Carson Valley Inn, Minden, Nevada

This project involved a wetland mitigation plan, all design aspects of a wetland mitigation plan, construction implementation and monitoring of the created wetland system.

The created wetland consisted of:

  • wetland delineation and verification
  • avoidance analysis
  • 401 Water Quality Certification
  • an approved Nationwide Permit
  • functional assessment
  • sub-surface hydrological study
  • design drawings
  • supervision of construction in environmental sensitive drainage area to the Carson River

The mitigation was constructed in April of 1991. The five year compensatory monitoring requirement was completed in three years.