The Reno-Tahoe International Airport, Steamboat Creek Restoration Project

Reno, Nevada

This project involved over 800 acres of land with 14 acres of jurisdictional wetlands of which 4.64 acres were impacted by a proposed runway expansion project. The project was completed during 1994 and the mitigation has since satisfied the final success criteria. 7Q10 assisted the clients by obtaining:

  • wetland delineation and verification
  • avoidance analysis
  • 401 Water Quality Certification
  • functional assessment
  • approved Individual 404 permit
  • NDPES Permits
  • a detailed wetland mitigation plan which calls for the restoration of 3,500 feet of Steamboat Creek
  • channel design and restoration
  • construction implementation of 10.64 acres of mitigation wetlands
  • mitigation monitoring and compliance reporting